- Construction will continue as the weather allows.
- N. Main- Southbound is scheduled to open late next week.
- Sidewalks with ADA access are constructed and can be used from the NE Quadrant to the Courthouse.
- Sidewalk access at the SE corner of the Courthouse is usable but has wooden ramps.
- Porter Brothers will be concentrating work efforts near the SE corner of the Courthouse over the next few days.
- Please be mindful of areas marked with snow fence/caution tape. We are having issues of footprints in freshly poured concrete.
- Footprints slow production as the contractor has to repour those panels.
- Please use caution while walking in the NW quadrant and do not enter the red areas on the map.
***Courtesy of Jason Petentler| Resident Technician-Peoria, Hutchison Engineering***