Concrete Being Poured in Monmouth’s Southwest Quadrant

Courtesy of Jason Petentler | Construction Resident Technician

Share

Construction Activities (Week of 4/7/25)

  • Tuesday-large sidewalk concrete pour in front of the businesses on the SW Quadrant. Please find alternate routes for 24  hours. 
  • Pour scheduled for 11AM. 
  •  If the sidewalk has caution tape, fence, or barricades please DO NOT use. Several sidewalk panels have to be repoured due to footprints. 
  • Eastbound West Broadway is closed.
  • Southbound South Main is closed.
  • The SW quadrant parking is closed as heavy demolition is taking place. 
  • Business pedestrian access will be provided around the perimeter of SW quadrant business fronts. 
  • Gravel temporary access is provided. The best entrance is off S. Main Street.

***Courtesy of Jason Petentler | Construction Resident Technician, Hutchison Engineering***

Spread the word

Trending Now

Featured News Podcasts

Choose a Category

Continue Reading

City Council Meeting Summary 05.05.2025

Key Actions and Approvals Committee of the Whole Discussions Other Business Get Involved! Residents can speak at council meetings during the Citizen Inquiries section (3-minute limit). The next meeting date

One Voice Can Change a Life

CASA is the Court Appointed Special Advocate program. Their mission is to speak up for and support the best interests of abused and neglected children in the court system. CASA,