This Week’s Construction Activities (Week of 3/31)
- NW Quadrant- The gravel areas will be cored out and replaced with concrete.
- Westbound West Broadway will be opening this week.
- Southbound South Main will be closing this week.
- Ameren is scheduled this week to remove poles, wiring, and lights.
- East Broadway will remain open longer than anticipated. Porter Brothers decided to wait a little longer before closing.
- The SW quadrant parking is closed as heavy demolition is taking place.
- Business pedestrian access will be provided around the perimeter of SW quadrant business fronts.
- Gravel temporary access is provided. The best entrance is off S. Main Street.
***Courtesy of Jason Petentler | Construction Resident Technician, Hutchison Engineering***