Update on the Monmouth Square project. 

Traffic flow changes for next week-Monday (6/2) Porter Brother’s will be opening Southbound S. Main and Closing all of E. Broadway. 

S. Main-

  • Remaining construction will continue on S. Main and be priority. 

E. Broadway-

  • E. Broadway will be closed and the remaining demolition will continue. 
  • When sidewalks are removed, temporary rock will be reinstalled for foot traffic ASAP. 
  • Underground work and several foundation openings will be addressed. 

Please use extreme caution and follow the marked paths when traveling to businesses. 

***Courtesy of Jason Petentler | Construction Resident Technician, Hutchison Engineering***