Update on the Monmouth Square project.
Traffic flow changes for next week-Monday (6/2) Porter Brother’s will be opening Southbound S. Main and Closing all of E. Broadway.
S. Main-
- Remaining construction will continue on S. Main and be priority.
E. Broadway-
- E. Broadway will be closed and the remaining demolition will continue.
- When sidewalks are removed, temporary rock will be reinstalled for foot traffic ASAP.
- Underground work and several foundation openings will be addressed.
Please use extreme caution and follow the marked paths when traveling to businesses.
***Courtesy of Jason Petentler | Construction Resident Technician, Hutchison Engineering***