Monmouth Square Update
Porter Brothers plans to open W. Broadway in both directions.
Closed roads within the project limits-(as of Wed 5/14/25)
- Eastbound E. Broadway
- Northbound and Southbound S. Main Street
Work will continue on S. Main Street. The plan will be to open Southbound S. Main in 1-2 weeks.
Brick laying will continue in the SW Quadrant
Excavation of E. Broadway will begin over the next few days.
Please use caution as construction workers and equipment will be moving around the square.
***Courtesy of Jason Petentler | Construction Resident Technician, Hutchison Engineering***