Porter Brother’s has finished asphalt operations around the square. The square and quadrants are now open!!!
- Next week tinted crosswalks will be installed.
- Quadrants will be open.
- Only half of the crosswalks will be poured to allow the square to still operate.
- I will follow up with emails as the tinted crosswalks are installed.
- Painting operations will be the week of the 20th.
These dates are tentative and dependent of weather.
***Courtesy of Jason Petentler | Construction Resident Technician, Hutchison Engineering***