- Various lane closures as concrete patches will be poured back over underground trenches.
- Porter Brothers will be pouring patches at the South and East ends.
- Laverdiere will be working on patches at the North end, which is a different contract.
- Curb/Gutter & Island construction.
- Please avoid using the NE quadrant as major construction is taking place.
- Business foot traffic is open in the NE quadrant, please stay within the marked access areas along the front of the businesses.
- NE Quadrant Businesses- Handrailing is currently ordered, installing when it arrives. Ramps are currently poured from Kellogg Printing to the East. If there is caution tape and barricades, please do not step on the concrete as it is curing. If the barricades and tape are removed, you are more than welcome to use the sidewalk. If you need other arrangements, please let me know and I can see what Porter Brothers can come up with.
- The water bill drop box is temporarily closed during construction. Bills can be dropped off at City Hall or the Public Safety Building.
- Thank you for your patience and understanding as work continues.
***Courtesy of Jason Petentler | Resident Technician-Peoria, Hutchison Engineering***