Update on the Monmouth Square Project

Photo Courtesy of Prairie Communications

Share

  • Porter Brothers will be pouring sidewalk and ADA ramps by Stanton insurance tomorrow. This area will be closed for a couple days.
  • If areas are blocked off with snow fence, please do not step on the fresh concrete. 
  • The area by Stanton should be opened by Friday but may have osb wooden sheets to walk on during the weekend. 
  • Curb and Gutter will also be poured along the business fronts. 
  • It is recommended to enter businesses from the new courthouse sidewalk on the West side. 

Business fronts and the parking bump out areas near Stanton Insurance are a priority. The goal is to have all the sidewalks poured along the business fronts and N. Main opened back up within the next couple of weeks. The temperatures this week will stop concrete production after tomorrow. Next week’s weather looks better, and Porter Brothers plans to pour several days. 

The intent for the project is to continue on until the weather shuts production down. This usually happens when the concrete plants shut down. 

Please use caution around the Square as construction continues. 

***Courtesy of Jason Petentler – Resident Technician-Peoria, Hutchison Engineering***

Spread the word

Trending Now

Featured News Podcasts

Subscribe to our Community Newsletter

By submitting this form, you are consenting to receive marketing emails from: Prairie Communications, 55 Public Square, Monmouth, IL, 61462, https://977wmoi.com/. You can revoke your consent to receive emails at any time by using the SafeUnsubscribe® link, found at the bottom of every email. Emails are serviced by Constant Contact

Choose a Category

Continue Reading