Next Week’s Construction Activities (Week of 3/10)
* Both lanes of West Broadway will be closed.
* With the projected weather, concrete production will be ramping up.
* More equipment and supplies will be moved from the NW Quad to West Broadway.
* Brick laying will ramp up East of the courthouse.
* Lighting-Production delays have set back light pole arrival dates. The new projected date will be early May. To keep the contractor moving forward, Ameren will need to remove the remaining poles and wire that are currently operational. At no cost to the city, the subcontractor will be installing temporary lighting until the permanent lighting can be installed.
Please use caution as construction workers and equipment will be moving around the square.
***Courtesy of Jason Petentler | Construction Resident Technician***